CHIPS Act Restructuring: US Government Takes Intel Equity Stake as TSMC Arizona Accelerates and Ohio One Delays to 2030
The U.S. semiconductor reshoring landscape continues to reflect a dual narrative of rapid progress at foreign-led projects (such as TSMC Arizona and Amkor Peoria) and capital-constrained, slower-paced progress at domestic champion Intel Corporation. For its massive "Ohio One" project in New Albany, Ohio, Intel is executing a financially disciplined, slower build schedule to manage its capital expenditure in alignment with broader market demand.
Intel Ohio One Capex and Investment Trends
In early March 2026, Intel submitted its annual progress report to the Ohio Department of Development, providing key transparency on its actual capital deployment and construction pace:
- 2025 Capex: Intel invested approximately $1.4 billion (or $1.5 billion according to local business journals) in Ohio during 2025. This reflects a deceleration in spending aligned with the company's July 2025 decision to slow construction.
- Cumulative Investment: Over the three years since selecting Licking County in 2022, Intel has invested more than $5 billion in the Ohio One project (out of a planned $28 billion total investment for the two-fab campus).
- Supply Chain Integration: Despite the slower construction pace, Intel has successfully integrated local businesses. Its active Ohio supplier base has grown from 150 companies in 2022 to nearly 450 collaborations as of December 2025.
Construction Timeline and Operational Targets
In its March 2026 report, Intel reiterated its commitment to the project and stated it is not anticipating further delays beyond the revised timeline established in 2025:
- Fab 1 (Mod 1): Construction completion is targeted for 2030, with commercial operations expected to begin between 2030 and 2031.
- Fab 2 (Mod 2): Construction completion is targeted for 2031, with commercial operations expected to begin in 2032.
Currently, several hundred trade workers remain active on-site. Intel has achieved its "go vertical" milestone (completing the sub-utility trenches and fab basement) and is proceeding with above-ground structural steel and office building construction. To prepare for eventual operations, Intel has already hired 162 local employees, most of whom are currently training at its active fabs in Arizona, New Mexico, and Oregon.
While the slower capex pace reflects Intel's broader corporate restructuring and capital constraints, the project remains a cornerstone of the domestic semiconductor manufacturing base, albeit on a decade-long horizon1 rather than the rapid ramp-up initially envisioned.
-
An instance of Sovereign manufacturing reshoring plateaus the moment easy grants and cheap capital dry up. — It shows how corporate capital constraints and market realities slow the initial momentum of domestic fabrication megaprojects, dragging out timelines over a decade. ↩︎