New AI load must now bring its own generation or stand first in line for curtailment.

FERC's show-cause reforms are pushing all six RTOs to exclude new large loads from capacity-market procurement, require self-supplied or co-located generation, and register un-backed loads as interruptible — shifting resource-adequacy costs and reliability risk entirely onto data-center developers.

1
Topics it spans
2
Findings citing it
—
Evidence window
The convergence

The same conclusion keeps arriving from across the workspace's research — 1 topics independently instantiate this theme. Filter the evidence by where it came from:

The AI Power Bill
PJM's Reliability Backstop Procurement: FERC Accepts but Suspends — the September Auction Never Happened

PJM's IRAS framework forces hyperscalers to either self-supply new generation or accept first-off curtailment in grid emergencies, shielding ordinary ratepayers from their capacity costs.

The AI Power Bill
FERC Section 206 Show-Cause Filings: RTOs Propose Landmark "BYONG" and Capacity Market Exclusions

ISO-NE's blueprint makes data-center developers solely responsible for their own resource adequacy while the capacity market procures nothing on their behalf, the structural endpoint of the bring-your-own-generation regime.